Call for Tenders A/O 2009-02
Wind Power – 2 X 250 MW

Answers to bidders' questions

IMPORTANT !
The answers to the following questions have been revised :
Q11 (2009-06-30), Q2 (2009-06-08)
November 20, 2009 Q40 Section 2, Article 2.10

Question (translated from French):
About the analysis of wind conditions, the call for tenders document indicates that the total data recovery rate at the site, which is, by the definition provided, the average recovery rate calculated for each meteorological mast must be at least 75% during the mandatory period of eight months measurement period at the site. However, a minimum of only one meteorological mast, for each wind farm offered, is required for wind assessment. If we have more than one meteorological mast installed on site to conduct the wind assessment, can we calculate the recovery rate with only one of these masts, provided that it meets the requirements of the call for tenders document? The additional masts on the site would be considered as additions to the analysis.

Answer :
Download the answer

November 2, 2009 Q39 Appendix 12

Question (translated from French):
In Section 5.1.2 of Appendix 12, it is written: "the bidder must provide an adequate proof showing that a majority of the members or shareholders (Editor's note : of the cooperative) have their official domicile in the administrative region where the community project is located (copy of the driving licence)". Question : Must the cooperative be legally incorporated et have members duly recognized before bid submission?

Answer :
Download the answer

October 7, 2009 Q38 Appendix 12, Article 3.2.4.1

Question (translated from French):
Can a bidder submit option agreements that become valid upon expiration of those already signed with another proponent not awarded a contract in a prior call for tenders?

Answer :
Download the answer

October 7, 2009 Q37 Section 1, Article 1.3.1.1

Question (translated from French):
Can a Aboriginal wind project be developed in an administrative region where there is no Aboriginal nation or community recognized by the Government of Quebec?

Answer :
Download the answer

October 7, 2009 Q36 Section 1, Article 1.3.1.1

Question (translated from French):
Can an Aboriginal nation or community develop a project in an administrative region different from where this Aboriginal nation or community, recognized by the Government of Quebec, is located?

Answer :
Download the answer

October 7, 2009 Q35 General

Question (translated from French):
Is it possible to obtain from Hydro-Quebec Distribution the environmental data and the wind measurements already presented by a bidder in an earlier call for tenders, but which the project was not accepted?

Answer :
Download the answer

October 7, 2009 Q34 Section 2, Article 2.2.10

Question (translated from French):
In Section 2.2.10 of the call for tenders document, it is mentioned for purposes of establishing the total data recovery rate, the reconstitution of missing data from a calibrated instrument based on data from another instrument (calibrated or uncalibrated) is acceptable provided that a correlation coefficient equal to or greater than 0.95 is established between the two wind measurement instruments.

Can you specify the time period (for example, a total of 8 months, a sub-period representative of the shortfall, etc…) when the correlation coefficient should be calculated?

Answer :
Download the answer

October 2, 2009 Q33 Section 1, Article 2.2.10

Question (translated from French):
Following Question 31, it states that "A project equipped with a meteorological mast located at a distance no longer than 4 km of the nearest wind turbine is acceptable if a verification is made by a second meteorological mast located at a maximum distance of 2 km of the same wind turbine." Is Hydro-Quebec prepared to accept a distance of no more than 6 km, instead of the4 km currently accepted?

Answer :
Download the answer

September 28, 2009 Q32 Appendix 2

Question (translated from French):
Does the submission of the registration form "Notice of Intent to bid" presented in Appendix 2 of the call for tenders documents and registration fees commit us to submit a bid? Are we required to submit a bid in May 2010? If yes, what are the penalties for not submitting? Is it simply a registration in order to be able to submit a bid on May 19, 2010?

Answer :
Download the answer

September 28, 2009 Q31 Section 1, Article 2.2.10

Question (translated from French):
Is a project with a meteorological mast located at a distance of 4 km from the nearest wind turbine acceptable if a second meteorological mast is installed at a maximal distance of 2 km of the same wind turbine? If yes, what are the conditions of validity (duration, correlation coefficients, etc.)

Answer :
Download the answer

September 28, 2009 Q30 Section 1, Article 1.3.1.1

Question:
Can one Aboriginal Community, which is part of a larger Aboriginal Nation, submit two projects of 25MW?

Answer :
Download the answer

September 24, 2009 Q29 Section 2, Article 2.2.3

Question (translated from French):
Starting from the principle that a corporation’s equity is made up of ordinary share capital (voting and participating), participating share capital (voting or non-voting, with or without interest), and accrued profit/losses less dividends paid and, in the event that the financial structure that was set up includes a portion of voting and participating shares and another portion in participating share capital, where a partner community must hold at least a 30% shareholder interest in the capitalization of a wind farm project in terms of shareholders’ equity, is the community’s participation and 30% interest in the voting share capital of a company in operation considered to be shareholders’ equity?

Answer :
Download the answer

September 22, 2009 Q28 Section 2, Article 2.5

Question (translated from French):
We received the results of our exploratory study, which contains a connection cost in 2009 dollars. To properly interpret the results in terms of our project’s competitiveness, we would like to obtain the kilowatthour (kWh) cost similarly to what was stated when the successful bidders for the 2000-MW call for tenders were announced (for instance, as provided on page 30 of exhibit HQD-2, document 1 submitted to the Régie).

Answer :
Download the answer

September 21, 2009 Q27 Section 3, Article 3.5

Question (translated from French):
If our company is registered as a bidder, can our community or Aboriginal partner use our user code received during registration to ask questions via Hydro-Québec Distribution's website?

Answer :
Download the answer

September 17, 2009 Q26 Appendix 6

Question (translated from French):
Could Hydro-Québec TransÉnergie's exploratory study report provide us with details on the level of receptivity of the connecting zone?

For instance, could we be informed on the total integration capacity (in MW) available for the line indicated by Hydro-Québec TransÉnergie and/or for all the lines of the system for that zone?

Answer :
Download the answer

September 17, 2009 Q25 Appendix 6

Question (translated from French):
In the exploratory study request form, which information has to appear on the location map of the project? For instance, is the location of wind turbines required?

Answer :
Download the answer

September 10, 2009 Q24 Section 1, Article 1.10

Question (translated from French):
Where a bidder proposes two projects that are adjacent and of 25 MW each, whereas the possibility that a bid present a variant conditional on the acceptance of another bid, can the exploratory study inform us of the capacity of the transmission system to receive 50 MW? If yes, how should we proceed to present the request for exploratory study or studies?

Answer :
Download the answer

September 8, 2009 Q23 Section 2, Article 2.10

Question:
In follow-up to Question and Answer 3, would a project that has a meteorological tower 3 to 4 km from the closest wind turbine and verification within 2 km of the closest wind turbine using SODAR or LIDAR be viewed as meeting the requirements of the article?

Answer :
Download the answer

September 1, 2009 Q22 Section 2, Article 2.5

Question (translated from French):
If the costs provided by HQT following a request for an exploratory study are expressed in project investment dollars, please provide the formula or factor used by HQD to convert this amount into dollars per year, which are added to the price of annual generation in order to compare the energy purchase cost assessed by HQD between two projects.

Answer :
Download the answer

September 1, 2009 Q21 Section 1, Article 1.9

Question (translated from French):
Can a project contain several switchyards ?

For instance, is it acceptable to present in a single bid, a 24MW project in which wind turbines are located in three non adjacent locations and are connected to the power system through three different switchyards ?

Answer :
Download the answer

August 20, 2009 Q20 Appendix 2

Question (translated from French):
Q1) What are the requirements regarding the registration form for a private developer who intends to present several projects in the present call for tenders under different legal entities to be created (with several community and native partners)?

Q2) Will a developer who registers on his own behalf be authorized to present several bids with different community, native and private partners under legal entities to be created?

Q3) Is it rather the community or native partner who needs to register?

Answer :
Download the answer

August 4, 2009 Q19 Section 2, Article 2.10

Question (translated from French):
Does the wind data required in the present call for tenders be absolutely captured during the years 2009-2010? For example, is it possible to reuse the wind data presented in the 2nd call for tenders?

Answer :
Download the answer

August 4, 2009 Q18 Section 2, Article 2.3

Question (translated from French):
Does a community, as a partner, invest financially in order to participate in the capitalization and control of a wind farm? For example, could a community participate in 30% of the capitalization and control of a wind farm by investing only 1 dollar ?

Answer :
Download the answer

July 27, 2009 Q17 Section 1, Article 1.10

Question (translated from French):
The potential bidder intends to submit a 25 MW project and must pay an amount of $ 5,000 for the exploratory study. Should the wind turbines of the same project be located in three areas that require three different connections instead of one, must the potential bidder pay $ 5000 three times because there are 3 connections, or $ 5000 given that it is the same project. (e.g. for wind potential reasons on a project made of 12 wind turbines, 6 may be in municipality X, 3 others in municipality Y and 3 others in municipality Z, which would require connection on three different points). Is it a single exploratory study for a single project?

Answer :
Download the answer

July 21, 2009 Q16 Section 1, Article 1.10

Question (translated from French):
If we wish to propose more than one project of 25 MW located in the same area and all connected to a single point of delivery, how should we proceed to complete the request for an exploratory study?

Answer :
Download the answer

July 10, 2009 Q15 Appendix 2

Question (translated from French):
We are planning to register for Hydro-Quebec Distribution Call for Tenders A/O 2009-02. If we are going to bid under different company names, (e.g. Company A is owned by Company XYZ and bids for community project 1 (25MW), Company B is also owned by Company XYZ and bids for community project 2 (another 25MW), and so on) do we need to submit separate Registration Forms for each Company A, B or can we just submit one Registration Form for Company XYZ?

Answer :
Download the answer

July 10, 2009 Q14 Section 2, Article 2.3.4.2.1

Question (translated from French):
In a case where the Supplier is owned by two owners, a community on one hand and a private company on the other hand, can the private company lend to the community to finance the community's participation in the Supplier? In this case, please confirm that the participation in the Supplier by the community is part of the community's equity and participation.

Answer :
Download the answer

July 10, 2009 Q13 Section 2, Article 2.3.4.2.1

Question (translated from French):
In a context of implementing its security, could a lender sell the project to a third party who is not a community? In other words, does Hydro-Québec accepts that, to the extent that a lender takes possession of the project for failure by the Supplier, the condition of continued participation of the community becomes obsolete? Otherwise, how can the community fund its participation in this project?

Answer :
Download the answer

June 30, 2009 Q12 Appendix 12, Article 3.7.5

Question:
As of June 30, 2009, the answer to question 11 has been revised. Please refer to it.

Answer :
Download the answer

June 29, 2009 Q11 Appendix 12, Article 3.7.5

Question (translated from French):
Must a wind turbine manufacturer already selected in the previous call tenders (2000MW) resubmit the wind turbine modeling before July 1st 2009? Can the manufacturer certify by letter that he has already submitted the information requested in the present call for tenders and confirm that the proposed wind turbine still complies as of today?


Answer (revised on 2009-06-30) :
Download the answer

June 10, 2009 Q10 Appendix 12

Question (translated from French):
In Section 3.7.5, it is mentioned : "the information required for the modeling of the electrical behaviour of the wind energy technologies must be transmitted to the Official Representative by the designated wind turbine manufacturer no later than July 1, 2009".
Can a bidder pass on this information in the wind turbine manufacturer's name?

Answer :
Download the answer

June 10, 2009 Q9 Appendix 7

Question (translated from French):
Please confirm that it is possible to connect a community or Aboriginal wind farm to an existing wind farm's substation.

Answer :
Download the answer

June 8, 2009 Q8 Section 1, Article 1.10

Question (translated from French):
As of June 8, 2009, the answer to question 2 has been revised. Please refer to it.

Answer :
Download the answer

June 8, 2009 Q7 Appendix 6

Question (translated from French):
As a follow up to Answer 2, in the case where a potential bidder asks for an exploratory study with a model of a wind turbine which has received a prior notice of qualification regarding the modeling of the electrical behaviour of each proposed wind energy technology (« Avis préalable de qualification relatif à la modélisation du comportement électrique de chaque technologie éolienne proposée »), please clarify why it is necessary to submit to HQ an notice which HQ supplied itself? Also, it is not very probable that the wind turbine manufacturer commits today that the electrical characteristics are identical until 2014. The possible modification of the electrical behaviour is an issue which, logically, the bidder has to manage with the manufacturer. The objective is, after all, an exploratory study. Please confirm that if an exploratory study request is submitted for a wind turbine model for which HQ has already emitted a notice, it will not be necessary to supply to HQ a copy of its own notice.

Answer :
Download the answer

June 4, 2009 Q6 Section 1, Article 1.3.1.2

Question (translated from French):
"A community wind energy project is defined as a project that: - is recognized by the RCM where the project is located" The question is as follows: Can a RCM , by resolution, recognize more than one project of 25 MW on its territory?

Answer :
Download the answer

June 4, 2009 Q5 Section 1, Article 1.3

Question (translated from French):
We have a question concerning the case of the 250 MW block stemming from Aboriginal projects and the definition of "Aboriginal nation". Is there a distinction between the Aboriginal communities within the same First nation? For example, are Mingan (Ekuanitshit) and Uashat de Maliotenam representing two different Aboriginal nations or are they part of the only one?

Note that they each have their territory in a different MRC and they recognize themselves as being two different Aboriginal communities. On the other hand, they are both a part of the Innu (Montagnais) community.

Answer :
Download the answer

May 20, 2009 Q4 Section 2, Article 2.2.10

Question (translated from French):
"The wind conditions must be evaluated using at least one meteorological mast for each wind farm being proposed."

Is it necessary to understand that each bid has to use a different mast? Can the same mast be used for two independent bids which are near each other?

Answer :
Download the answer

May 20, 2009 Q3 Section 2, Article 2.2.10

Question (translated from French):
How is define the 2km limit between the meteorological mast and the wind farm ? Is it a distance between the mast and the nearest wind turbine? Between the mast and the center of the wind farm? Between the mast and a physical limit of the wind farm?

Answer :
Download the answer

May 15, 2009 Q2 Section 1, Article 1.10

Question (translated from French):
Q1) Please confirm that the exploratory study report prepared by Hydro-Québec TransÉnergie will be made available only to the potential bidder requesting such study and that the exploratory study request, including the potential bidder’s name and the wind farm project site, will be kept confidential.

Q2) In the event that a exploratory study request concerns a manufacturer and a wind turbine model for which information has already been provided to HQD in relation to the 2000-MW call for tenders, please confirm that Hydro-Québec TransÉnergie can carry out the exploratory study even if the manufacturer is not yet registered and/or has not submitted the same information again.

Q3)
a. Please confirm that the expression “additional variant” in Section 1.10.2 really means a third project variant as stated in Section 3.12 of the call for tenders document and that, as a result, an exploratory study at a cost of $5,000 will allow the potential bidder to obtain an idea of the feasibility of its project’s connection with three wind turbine models (main project and two variants), which will allow the potential bidder to direct its discussions with potential manufacturers as well as to eventually offer HQD as many technological options as possible in the same bid.

b. If the answer to 3 a) is no and considering that:

i) without a minimum number of orders for the manufacturers in call for tenders A/O 2009-02, the barriers to entry for manufacturers who did not bid on the 2000-MW call for tenders are very high;

ii) HQ received, studied and simulated the wind turbine models of at least three manufacturers for the 2000-MW and 1000-MW calls for tenders;

iii) the exploratory studies for a given site and capacity must include a significant common portion for different wind turbine models;

iv) the manufacturers will not provide their prices and conditions in the last months before call for tenders A/O 2009-02 is closed.

Therefore, would HQ agree to have the exploratory studies for a main project and two variants for the same site and same installed capacity but with three wind turbine models and for which all of the technical information has been filed for the 2000-MW call for tenders carried out for $5,000?




Answer (revised on 2009-06-08) :
Download the answer

May 13, 2009 Q1 Section 1, Article 10.2

Question (translated from French):
I would like to know if it is required to be registered et have paid the registration fees in order to request an exploratory study for the connection of the wind farm.

Answer :
Download the answer

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security

© Hydro-Québec, 1996-2009. Tous droits réservés.

Logo Hydro-Québec