Power Transmission Projects

Integration of Wind Farms – 1st call for tenders (2003)

At a Glance
Status: Under study and under construction
Region: Bas-Saint-Laurent-Gaspésie
Type: Growth in energy requirements
Owner: Hydro-Québec TransÉnergie
Project supervision: Hydro-Québec Équipement
Documents
Wind mill

In October 2004, following a first tender call for the purchase of wind power, Hydro-Québec announced the acceptance of eight bids totalling 990 MW.

To ensure safe, reliable transmission of electricity produced by the eight new wind farms, Hydro-Québec Équipement will do a great deal of work on the Gaspé transmission grid (special protection systems, telecommunications, lines and substations).

To integrate the planned facilities harmoniously with their surroundings, Hydro-Québec will conduct technical, economic and environmental studies within the study areas. The company will also hold information and consultation sessions with stakeholders and citizens.

1. New lines

Project Length Commissioning Status For further information
230-kV
Les Méchins wind farm line
4 km 2010 Under study
230-kV
Goémon–Mont-Louis–Gros-Morne line
90 + 18 km 2011 Under study
161-kV
Montagne-Sèche wind farm line
36 km 2011 Under study

* In French only

 

2. Reinforcement of existing lines

  • 230-kV Les Boules–Matane line (under construction)
  • 230-kV Matane–Goémon line (under construction)

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security