Power transmission – Integration of wind farms
| Status: | Under construction |
| Region: | Capitale-Nationale |
| Owner: | Hydro-Québec TransÉnergie |
| Project supervision: | Hydro-Québec Équipement et services partagés |
In French only
Seigneurie de Beaupré
This construction project will connect the Seigneurie de Beaupré wind farms to Hydro-Québec's transmission grid. The planned installed capacities of Seigneurie de Beaupré-2 and Seigneurie de Beaupré-3 are 132.6 MW and 139.3 MW respectively, totalling 271.9 MW.
The wind farms are among the fifteen projects selected in Hydro-Québec's second round of tendering for the purchase of wind power.
Hydro-Québec plans to build a 315-kV single-circuit line about 15 km long to connect the planned wind farm's switchyard to the existing Bersimis-Laurentides line. The project includes the creation of a loop to Charlevoix substation by building a 315-kV double-circuit tap line, about 3 km long.
Construction is planned for January to April 2013, with commissioning in summer 2013.
To learn more about the project, consult the Documents section above.