<

A project for sustainable development

Project Description

View animation

The project consists of three main components:

  • Construction of a 768-MW powerhouse, Eastmain-1-A, near the existing Eastmain-1 powerhouse
  • Construction of a 150-MW powerhouse, Sarcelle, at the outlet of Opinaca reservoir
  • Partial diversion of the Rivière Rupert to these two generating stations and from there to Robert-Bourassa, La Grande 2-A, and La Grande-1 generating stations
Simulation barrage Rupert
Simulation of Rupert dam

The Rupert diversion includes the following structures and facilities:

  • Four dams
  • A spillway, which will also function as an instream flow release structure, on the Rupert
  • 74 dikes
  • Two diversion bays (forebay and tailbay) with a total area of about 346 km2; at maximum operating level
  • A 2.9-km-long tunnel between the Rupert forebay and tailbay
  • A network of canals with a total length of about 12 km to facilitate flow in the various portions of the diversion bays
  • Hydraulic structures on the Rupert River to maintain post-diversion water levels along approximately 48% of the river's entire length
Simulation centrale Sarcelle
Simulation of Sarcelle dam

Also part of the project is the construction of a new drinking-water plant in Waskaganish, which will meet the needs of the community until 2025.

To bring the output from the new generating facilities onto the power grid, 315-kV lines will be built between Eastmain-1 and Eastmain-1-A and between Sarcelle and Eastmain-1.

The project, scheduled for commissioning in 2011–2012, will give Hydro-Québec's generating fleet additional capacity of 918 MW and additional output of 8.7 TWh per year, distributed as follows:

Simulation centrale Eastmain-1-A
Simulation of Eastmain-1-A powerhouse
  • Marginal gain at Eastmain-1-A and Eastmain-1 powerhouses: 2.3 TWh.
  • Output at Sarcelle powerhouse: 1.1 TWh.
  • Additional output at Robert-Bourassa, La Grande-2-A and La Grande-1 generating stations: 5.3 TWh.

Technical innovations

Nemiscau-1 dam

Core to be constructed of asphalt concrete. Well known in Europe, this technique is used in the absence of till to ensure that a structure is watertight.

Although there is no lack of till in the Nemiscau area, Hydro-Québec wishes to adopt this technique for use in future projects in northern regions, such as those being carried out on the Romaine River, where till is harder to find.

Eastmain-1-A powerhouse

The superstructure will be built of components prefabricated at the jobsite and then transported to the powerhouse site for assembly. One of the advantages of this method is that it speeds up the work.

Sarcelle powerhouse

Installation of bulb-type turbine generating units-a first for Hydro-Québec. Bulb-type units, where both the turbine and generator are housed within a watertight metal casing, work well in situations where there is little hydraulic head (about a dozen metres at the Sarcelle site) and high flow.

Schedule


Activities
2004 2005 2006 2007 2008 2009 2010 2011 2012
T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4
Impact statement filed Livraison
Screening analysis Livraison
Authorizations received Livraison
Partial diversion of the Rupert Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Livraison
Eastmain-1-A powerhouse Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Livraison
Livraison
Livraison
Sarcelle powerhouse Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Période travaux Livraison Livraison
Livraison
Construction period Construction period       Delivery Delivery or commissioning of generating unit

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security

© Hydro-Québec, 1996-2010. All rights reserved.

Logo Hydro-Québec