Hertel‑New York interconnection line

Work completion: December 2025
Commissioning: May 2026

See photos of the work

Three ways to stay informed and to plan your trips

Sign up for text alerts (SMS) about traffic disruptions.

Consult the interactive map of the work and traffic disruptions.

Sign up for the project newsletter.

Project overview

The Hertel‑New York interconnection line project aims to supply clean, renewable energy to New York City. In Québec, the project involves the construction of a line that will span 57.7 km (56.1 km underground and 1.6 km underwater). This 400-kV direct current line will connect Hertel substation in La Prairie to an interconnection point in the Rivière Richelieu at the Canada–United States border.

The project also includes installing a converter at Hertel substation. It will convert alternating current to direct current to supply the new interconnection.

The new line will connect to the line planned under the Champlain Hudson Power Express (CHPE) project, overseen by Transmission Developers Inc. (TDI) in the U.S. The CHPE project involves building an underground and underwater DC line between the Canada–U.S. border and New York City, a distance of roughly 545 km. In addition to receiving all required authorizations in the U.S., this project has been selected by the authorities of New York State to deliver hydropower to the heart of New York City.

Location and status of the project

Lighting New York City with Our Clean and Renewable Energy

Prevents the emission of approximately 3.9 million tonnes of greenhouse gases annually

line about 60-km
underground

Addition of a converter at Hertel substation

Allows for the export of 1,250 MW of power

The project in videos

Project overview

Sébastien Bélanger, project manager, explains the project justification.

Duration: 1 minutes 27 seconds

The environment: At the heart of everything we do!

Valérie Groison, environmental project manager, explains the environmental approach.

Duration: 2 minutes 56 seconds

Understanding the work

Michel Laboissière, transmission line project engineer, explains the underground line work.

Duration: 2 minutes 53 seconds

Understanding electric and magnetic fields and stray voltage

Jean-Pierre Tardif, science communications advisor, explains the electric and magnetic fields and the stray voltage.

Duration: 3 minutes 02 seconds

Answers to your questions

Other questions?

See our FAQ page

Project schedule

  • Spring 2021 Public consultation
  • Fall 2021 Solution selected
  • Winter 2022 – Summer 2023 Government approvals
  • Fall 2023 Start of construction
  • Spring 2026 Commissioning

Project background

A first version of the project was developed in Québec in 2012–2013, when the draft-design studies and public consultations were carried out. In fall 2020, Hydro‑Québec teams contacted community organizations again and began updating its environmental surveys and collecting field data.

Additional studies and surveys were then carried out to identify the technical and environmental optimizations required to adapt the initially proposed project to current needs and circumstances.

Hydro‑Québec also collected public input to learn more about the project’s environment and minimize impacts during construction. Comments and questions from community organizations, the general public and land users have helped improve the project.