Power transmission
There are nine main steps to build a substation to lower the voltage generated by transmission lines, and it takes many tradespeople to meet the challenge. At each step, we adopt strict safety, project quality and environmental protection practices.
Before carrying out any work, it is important to establish the work zone and fence it off to ensure the safety of the access points.
Then, notices of work and site tags are installed to keep citizens informed throughout the construction period. In addition, other sources of information — including a Web page, an Info-project line, project news bulletins and press releases — are generally available to citizens, who may also contact the project's community relations advisor.
Throughout the project, site supervisors ensure that all the actions undertaken meet environmental, health and safety and quality standards.
At this step, any trees growing in the work zone are cut down.
Then, the ground is levelled and earthwork is carried out.
The construction team prepares the work site by carefully setting aside the topsoil, which will be reused.
At this step, workers excavate the site, build the formwork, install the reinforcements and pour the concrete.
In addition to laying the foundations, we build all the underground concrete structures, such as the recovery basin.
The grounding grid is installed to ensure the safety of people and the equipment. Buried underground, the grid redirects the fault current.
As its name suggests, the command building houses the control and protection equipment.
Most substations are automated and remotely controlled. Only the largest substations have permanent technical staff on site since most are maintained by mobile teams.
Once the foundations have been laid, we backfill them and level the yard with granular material (sand, gravel, rock, etc.) that is adapted to the site.
Once the concrete is set, steel structures are assembled to support the electrical equipment. Other structures will support the control building.
Once the framework is built, we install the equipment on the foundations and steel structures.
For more information on the different types of equipment, click on the following links.
Each piece of equipment is then connected to the control room, which is under construction.
We permanently fence off the new installations to ensure everyone's safety. Our technicians test the equipment before the installations are connected to the power grid. Finally, we commission the substation and ensure that the electricity is flowing.
Follow the link to find out How a substation works and learn more about the different types of equipment that are installed.
The project ends with landscaping: we plant trees, create mounds of earth and do more work if necessary.
We do earthwork, demobilize the site and carry out the final inspection to wrap up the project. Only the operating equipment is left at the substation.
© Hydro-Québec, 1996-2025. All rights reserved.