Appalaches-Maine Interconnection
Work
Hydro‑Québec has obtained all the necessary government approvals to begin construction of the Appalaches‑Maine interconnection line. After resuming land clearing and access road construction work in the summer of 2023, Hydro‑Québec is now undertaking the next steps in the construction of the line spanning some 100 km.
Work progress – January 2025
At time of writing, work at Appalaches substation in the municipality of Saint‑Adrien‑d’Irlande is roughly 75% complete. Construction of the 320‑kilovolt (kV) direct‑current interconnection line, in turn, is about 91% done.
Work at the substation is progressing well. Some 80 workers are currently on the job.
Activity | Completion (%) |
---|---|
Electrical engineering and control work (e.g., equipment installation) | 80% |
Delivery of power transformers (2 of 4) The two remaining power transformers will be delivered in 2025 (in spring, after the thaw, and in fall). |
50% |
Converter building | 95% |
Work is now complete in the southern section of the line under construction, most of which is located in Estrie. Site restoration is scheduled for the spring.
In the northern section of the line route, most of which is located in the Chaudière‑Appalaches region, the tower foundations and tower assembly are now complete. Some 70 workers are currently on the job.
Activity | Completion (%) |
---|---|
Tower raising | 88% |
OPGW stringing | 63% |
Cable stringing | 40% |
Steps in line construction
Work schedule and jobsite surveillance
Work on the route’s southern section, on the border with Maine, is scheduled to start in January 2024. Work will then progress northwards to reach Appalaches substation, with a view to commissioning the line by late 2025. Hydro-Québec will supervise the jobsite in compliance with applicable technical, environmental and safety requirements. Specific measures to mitigate the impact of the work will be implemented for harmonious coexistence with land users.
See the Project newsWorks contractor
The line (northern and southern sections) will be built by the general contractor GLR inc.
Contact info:
Pierre-Olivier Roux, Project Manager
1095, rue Valets
L’Ancienne-Lorette (Québec) G2E 4M7
418 872‑7420
pierre-olivier.roux@glr.qc.ca
Planned line route (northern and southern sections)

Download the map of the planned line route [PDF 200 kB – in French only]
Exercise caution around the jobsite
An increase in traffic and the presence of trucks and heavy machinery are expected along the future line and around the substation. We will make every effort to avoid road closures, but if they are necessary, appropriate signage will be erected to ensure a safe environment for the public and for workers. In principle, work will be carried out from Monday to Friday between 7 a.m. and 5:30 p.m. Hydro‑Québec wishes to thank those affected by the work for their understanding and urges them to exercise caution around the jobsite.

Info-Project – Appalaches-Maine Interconnection
Stay informed on the stages of the project and the progress of work.
Subscribe to Appalaches-Maine Interconnection newsletter