Answers
Rates, Conditions of Service and General information
1 - Does Hydro‑Quebec provide leasing services or sell generator for medium-voltage electricity?
2 - Does an application have to identify a specific location where the electricity will be used?
3 - What information should be included on the Tender Form where it asks "Number of addenda received"?
4 - Is the request for proposals only open to facilities in Quebec?
5 - We are already a connected customer since December 2017 with a 400 AMP service line. We have already invested heavily in our infrastructure and are prepared for an additional 400 AMPs. How does this affect our bid and will a new contract completely replace our existing one?
6 - With reference to page 51-53 of Annex 9: Can the bidder submit for a specific tariff in the bidder (e.g. Tariff M or Tariff L?) Or the application of the electricity tariff is imposed by Hydro‑Quebec based on evaluation of the bidder capacity?
7 - What are the locations eligible for use high-voltage electricity power? Can the bidder request Hydro‑Quebec to verify in advance that its intended location for the project is eligible for use of high-voltage electricity power?
8 - What are the locations eligible for use medium-voltage electricity power? Can the bidder request Hydro‑Quebec to verify in advance that its intended location for the project is eligible for use of medium-voltage electricity power?
9 - What are the required licenses for the bidder to build and connect to the electrical and to connect to the electricity grid of Hydro‑Quebec? Or Hydro‑Quebec will build and connect the bidder’s cryptocurrency mining system directly to the electrical grid?
10 - With reference to page 51 of the Tender Form, does the total investment capital includes all management cost for a period of 5 years? Or a longer/shorter period?
11 - Ref Annex 5 - Can the individual bidder submit a bank guarantee issued under the requested of a Canadian enterprise (because an individual bidder is not permitted to request to issue a bank guarantee at a Canadian bank)?
12 - Ref Art 3.2 RFP - What information should the investor include in the business plan?
13 - Would it be possible to get a copy of results from the third party survey you conducted with block chain companies in Summer 2018?
14 - Our question is related to section 4.2.2 of the Tender Form: When does the signed and sealed report from an independent engineer need to be submitted? With the submission of the Tender Form or at a later time?
15 - Who can be a director of a cryptomining company in Quebec? What are other requirements for such company?
16 - If a contract has not yet been signed with a user of the recovered energy, how detailed must the letter of intent? Must the letter of intent have the details required in a contract with a user of energy?
17 - Will the increased load resulting from the implementation of crypto mining activities on an industrial site with a Rate L supply contract be taken into account in the calculation regarding the Electricity Discount Program for Rate L Customers?
18 - Is an industrial customer with Rate L who installs crypto mining equipment eligible for Rate L if the equipment is connected to the interconnection?
19 - I would like to know what the disincentive rate is. Is it the amount added at all times to the regular rate (G or M)? My business is a startup that would like to start hosting blockchain machines. Would startups be able to a proposal?
20 - What is the average price per kWh? Are the conditions the same as for Rate M – business?
21 - Does Hydro Quebec provide leasing services or sell generators for medium‑voltage electricity?
22 - I would like to confirm the cost of electricity. According to my calculations, I would be charged at Rate M ($0.05/kWh) plus the $14.50/kW power rate for my project (192 kW). That works out to $0.07/ + taxes. Do my calculations seem correct?
23 - Once the Hydro-Québec request for proposals is finished, will it be possible to request a multi-MW connection for crypto mining use? What will happen when the request for proposals is over? Will all connection requests for this type of activity be rejected?
24 - If an industrial customer with Rate L installs a crypto-mining site in a facility with distinct metering dedicated to crypto mining and a distinct contract, can it use the same connection point for both uses? With distinct metering for crypto mining in place, the consumption for each type of use can be determined accurately.
25 - If my master electrician submits a request for a connection on my property for cryptocurrency purposes, do we have to apply under this request for proposals or can we submit a traditional connection request without going through this request for proposals?
26 - We are a group of investors who want to start a mining firm. We would like a complete description of the steps we have to take involving Hydro-Québec in developing project.
27 - Do we absolutely have to be a duly registered bidder to carry out our project?
28 - Would it be possible to get a copy of the results from the third-party survey you conducted with block chain companies in summer 2018?
29 - Who can be a director of a crypto-mining company in Québec? What other requirements apply for this type company?
RFP Process
1 - Does a bid have to identify a specific location where the electricity will be used?
2 - What information should be entered in the Tender Form where it asks "Number of addenda received," in section 1.1?
3 - Is the request for proposals open only to electrical installations in Québec?
4 - Is it possible to enter into an agreement involving a term of less than 5 years, for instance, one with a monthly or annual term?
5 - Is a financial guarantee required upon reaching an agreement and signing the contract?
6 - Why were the deadlines indicated in the request for proposals postponed by two months?
7 - In section 2.1.1 of the Tender Form (Annex 4), should the load factor (LF) calculation include or exclude the 300 uninterruptible hours?
8 - If the design report for the recovered energy reclamation process is not available at the time of the bid, is it possible to propose a concept that will be better defined at a later date?
9 - Does Section 4.2 still have to be filled out even though we do not recover any heat except from other building tenants, but no steps have taken?
10 - We are already a connected customer since December 2017 with a 400-amp service line. We have already invested heavily in our infrastructure and are prepared for an additional 400 amps. How does this affect our bid, and will a new contract completely replace existing one?
11 - Since we are already in production and integrated into the Hydro-Québec grid as a self-generator for cryptographic use and a Rate G consumer, how do Request for Proposals A/P-2019-01 and Rate M apply to our situation?
12 - Since we are already integrated into the Hydro-Québec grid and operating under the self-generation program without compensation, how should the contract power and load factor (LF) be determined in light of the framework presented in Request for Proposals A/P-2019-01 documents to ensure they meet our needs regarding the operation of our blockchain cryptography computers and application of Rate M? A related question: Will we be able to increase the contract power or decrease the LF at a later date if they are not appropriate for our needs?
13 - Is the operation of our power plant for cryptographic purposes under Hydro-Québec’s self-generation without compensation program, supplemented by the purchase of additional electricity from Hydro-Québec, consistent with the diversification target for projects under 5 MW advocated by the regulator for application of Rate M?
14 - In reference to pages 51 to 53 of Annex 9: Can a bidder propose a specific rate in its bid (for example, Rate M or Rate L)? Or is the applicable rate imposed by Hydro-Québec based on the power indicated in the bid?
15 - What locations are eligible for the use of high-voltage electricity power? Can the bidder ask Hydro Quebec to verify in advance that its intended location for the project is eligible for the use of high-voltage electricity power?
16 - What locations are eligible for the use of medium-voltage electricity power? Can the bidder ask Hydro Quebec to verify in advance that its intended location for the project is eligible for the use of medium-voltage electricity power?
17 - What licenses does the bidder require to build electrical installations and connect them to the Hydro-Québec grid? Or will Hydro-Québec connect the bidder’s cryptocurrency mining system directly to its electrical grid?
18 - In reference to page 51 of the Tender Form, does the total investment capital include all management costs for a five-year period, or for a longer/shorter period?
19 - In reference to Annex 5, can the individual bidder submit a bank guarantee issued at the request of a Canadian enterprise (because an individual bidder is not permitted to ask a Canadian bank to issue a bank guarantee)?
20 - In reference to Article 3.2 of the Request for Proposals Document, what information should the investor include in the business plan?
21 - In reference to Annex 5 – Irrevocable and Unconditional Standby Letter of Credit, we would like to know the amount of the guarantee required for our 192-kW project. Article 2.1 [sic] of the Request for Proposals Document indicates $10/kW based on the contract power. Does this mean that we must plan on $10/kW × 192 kW × 365 days = $700,800, or on $1,920? I would like a clarification, please.
22 - Reference: Article 1.6 of the Request for Proposals Document and Annex 7 – Standard Connection Agreement.
As indicated in the Summary of Selection Process, a parametric estimate of the costs associated with each project selected in step 3 will be provided to bidders. It is at this step that Hydro-Québec will be able to indicate whether there are costs associated with a specific project. Out of fairness to all bidders, no information regarding the load capacity of a specific site can be provided by Hydro-Québec for the purpose of preparing bids.
23 - My bank tells me that it takes five weeks to obtain a letter of credit. Could we provide a bank draft made out to Hydro-Québec if we cannot obtain a letter of credit by the deadline?
24 - In relation to Section 4.2.2 of the Tender Form, when does the signed and sealed report from an independent engineer need to be submitted? With the submission of the Tender Form or at a later time?
25 - Can the remaining balance of a sum deposited by a customer for a connection request in relation to which the project has been suspended be used to cover the bid bond called for in Article 2.3 of the Request for Proposals Document?
No, a sum deposited by the customer for a connection request filed with Hydro-Québec TransÉnergie cannot be used as a bid bond in connection with the request for proposals put out by Hydro‑Québec Distribution.
The bidder must enclose with its bid, at the time of submission, a bid bond of $10/kW based on the contract power, as required in Article 2.3 of the Request for Proposals Document.
In regard to the remaining balance of the sum deposited in relation to its connection request, the customer must contact Hydro‑Québec TransÉnergie.
26 - Our original agreement signed in Sept 2017 was for a 600 AMP 347/600 V connection. Are we not still entitled to that amount? Our current connection is 400AMPs.
A letter confirming the load associated to each of the existing contracts, as defined in the Rates and Conditions of Service for Cryptographic Use Applied to Blockchains, has been sent in mid-October 2019 to customers holding these contracts.
Holders of an existing contract wishing to participate to the request for proposals must enter, at section 2.1.1 of the Tender Form, the existing contract power. The proposal covers the contract power beyond this existing contract power.
(The terms indicated in italics are defined in Appendix 1 – Definitions.)