Project summary
Why?
- Pursue the development of wind potential in Eastern Québec.
- Improve grid resilience and reliability in the face of increasingly intense weather events.
How?
- Phase 1: Build a 735/315-kV substation and approximately 260 km of 735-kV lines.
- Phase 2: Build a 315-kV substation and approximately 175 km of 315-kV lines.
Commissioning
- Phase 1: 2034
- Phase 2: 2036